Echo Construction Project | November 2017-Current

Timeline of Construction Photos

November 6, 2017 Gym Concrete Block & Fitness Center Steel Framing in Place

1718-construction1.jpg

November 21, 2017 Classroom Wall & Roof Truss Framing

1718-construction2.jpg

November 28, 2017 Fitness Center Steel Truss Installation

1718-construction3.jpg

November 29, 2017 Office Area Glazing

1718-construction4.jpg

Entry Glazing Installation by Hermiston Glass

1718-construction5.jpg

December 5, 2017 Concrete Block Completed @ Gym Wall

1718-construction6.jpg

December 19, 2017 Gym Roof Trusses & Decking

1718-construction7.jpg

Gym Roof Framing & Fitness Area Wall Framing

1718-construction8.jpg

December 19, 2017 Agriculture & Science Classroom Wall Framing

1718-construction9.jpg

December 19, 2017 Fitness Center Wall Framing & Roof Decking

1718-construction10.jpg

December 23, 2017 Entry Vestibule Drywall

1718-construction11.jpg

January 4, 2018 Agricultural & Science Classroom Wall Framing

1718-construction12.jpg

January 4, 2018 Heated Enclosure for Concrete Block Work @ Community Room/Restroom

1718-construction13.jpg

January 22, 2018 Gymnasium Floor Concrete

1718-construction14.jpg

January 22, 2018 Community Kitchen Slab & Concrete Block Restrooms

1718-construction15.jpg

January 22, 2018 Agriculture & Science Classroom Framing

1718-construction16.jpg

January 30, 2018 Shop Area Concrete Blockwork

1718-construction17.jpg

January 30, 2018 Entry Area Roofing

1718-construction18.jpg